Burton Elementary School Addition
MONTHLY PROJECT UPDATES
April 2018
WORK ACTIVITIES: During the month the footings have been excavated, formed and poured. The under slab plumbing has been placed and rebar set and tied ready to be poured.
UPCOMING ACTIVITIES: The slab will be poured early in May. As soon as the slab is poured we will start the demo in preparation for the CMU walls to be erected and the trusses to be set. Once the roof has been sheathed, the dry-in process should begin by the end of May.
PROJECT SCHEDULE:
9%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|