Burton Elementary School Addition
MONTHLY PROJECT UPDATES
August 2018
WORK ACTIVITIES: Flooring was installed, ceiling tiles have been dropped into place, and temporary white boards have been installed. Mechanical, electrical, plumbing and fire protection (MEPF) trim work has been completed.
UPCOMING ACTIVITIES: The siding, soffit, and fascia will be installed about mid September. Landscaping work will wrap up and punch list and final cleaning work will start.
PROJECT SCHEDULE:
63%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|