WORK ACTIVITIES: Insulation work was completed at the beginning of July followed by the installation of the drywall.  Once the drywall was hung, taped, and textured the paint work began.
UPCOMING ACTIVITIES: The installation of the acoustical ceiling grid will begin at the beginning of the month.  Installation of the cabinetry will start once the grid is installed.  Once cabinetry is far enough along, the installation of the flooring will begin. At the end of the month the acoustical ceiling tiles will be installed followed by the installation of the tack boards and white boards.
Installation of drywall.
Painted walls.
Painted walls.
South elevation progress.

PROJECT SCHEDULE:

52%
Percent Complete
This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.