Kennedy Elementary School Addition

MONTHLY PROJECT UPDATES

June 2018


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES: The framing continued and was completed at the beginning of June.  The Mechanical, Electrical, and Plumbing (MEP) rough-in work started once the roof was dried in.  Insulation was installed in the walls and ceiling followed by the installation of the drywall on the ceilings.
UPCOMING ACTIVITIES: Taping and texturing will begin at the beginning of July. Painting will commence around the middle of the month.  Once painting is complete the installation of ceiling grid/tiles will begin.
Framing.
Drying in the roof.
Insulation installed.
Ceiling drywall.
Building wrap installed.
Wall insulation.

PROJECT SCHEDULE:

39%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.