Kennedy Elementary School Addition
MONTHLY PROJECT UPDATES
May 2018
WORK ACTIVITIES: The concrete slab was poured and finished in preparation for framing. The framing of the addition started including setting of the roof trusses.
UPCOMING ACTIVITIES: The framing will finish in early June. The next critical milestone will be completing the roof so the addition can be dried in. Then, mechanical, electrical and plumbing (MEP) rough-in work will begin. Once the MEP rough-in is complete the installation of the insulation will begin.
PROJECT SCHEDULE:
26%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|