Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
August 2019
WORK ACTIVITIES:
Dampproofing was completed on the inside of the building. Blueboard has been installed and the foundation backfilled. Once the foundation was backfilled the vapor barrier was placed and the sand and blueboard installed.
Dampproofing was completed on the inside of the building. Blueboard has been installed and the foundation backfilled. Once the foundation was backfilled the vapor barrier was placed and the sand and blueboard installed.
UPCOMING ACTIVITIES:
Slab to be poured at the gym floor. Masonry work will continue along with the electrical rough-in.
Slab to be poured at the gym floor. Masonry work will continue along with the electrical rough-in.
PROJECT SCHEDULE:
22%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|