Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
January 2020
WORK ACTIVITIES:
The painting of the ceiling in the gym was completed, and the CMU walls have been sealed. The hanging of the drywall under the mechanical mezzanine and stairs occurred about the middle of the month and the ceiling grid was installed in preparation for the panels to be installed. The Acoustical wall panels in the gym have been installed. Kitchen addition has continued with plumbing underground then pouring of the slab. Stair treads have been installed. Lighting has been hung throughout the project. The HVAC units are up and running. Windows have been installed.
The painting of the ceiling in the gym was completed, and the CMU walls have been sealed. The hanging of the drywall under the mechanical mezzanine and stairs occurred about the middle of the month and the ceiling grid was installed in preparation for the panels to be installed. The Acoustical wall panels in the gym have been installed. Kitchen addition has continued with plumbing underground then pouring of the slab. Stair treads have been installed. Lighting has been hung throughout the project. The HVAC units are up and running. Windows have been installed.
UPCOMING ACTIVITIES:
As soon as all the MEP rough-in at the mezzanine is complete the floor will be painted. MEP rough-in will be finished and trim out will begin. The polishing of the corridor will occur about the end of the month. Framing will begin at the kitchen addition mid-February. The demo at the tie in from the addition to the existing school will be completed. Door hardware will be installed.
As soon as all the MEP rough-in at the mezzanine is complete the floor will be painted. MEP rough-in will be finished and trim out will begin. The polishing of the corridor will occur about the end of the month. Framing will begin at the kitchen addition mid-February. The demo at the tie in from the addition to the existing school will be completed. Door hardware will be installed.
PROJECT SCHEDULE:
70%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|