Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
July 2019
WORK ACTIVITIES:
Footers and Foundations have been completed. Dampproofing is underway along with the blueboard installation so the backfilling can be done.
Footers and Foundations have been completed. Dampproofing is underway along with the blueboard installation so the backfilling can be done.
UPCOMING ACTIVITIES:
Dampproofing and installation of the blueboard will continue along with the backfilling of the foundation so the slab for the gym and new hallway can be poured.
Dampproofing and installation of the blueboard will continue along with the backfilling of the foundation so the slab for the gym and new hallway can be poured.
PROJECT SCHEDULE:
20%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|