Lincoln Elementary School Addition

MONTHLY PROJECT UPDATES

July 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:

Footers and Foundations have been completed.  Dampproofing is underway along with the blueboard installation so the backfilling can be done.
​
UPCOMING ACTIVITIES:
Dampproofing and installation of the blueboard will continue along with the backfilling of the foundation so the slab for the gym and new hallway can be poured.

17 foot gym wall
Slabs for future rooms
Damp-proofing back side of 17 foot wall
Door in fire riser room
New library room

PROJECT SCHEDULE:

20%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com