Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
March 2020
WORK ACTIVITIES:
Drywall work under the stairs was completed, the setting of the acoustical ceiling tiles has been finished. Installation of the interior doors was completed. Paint work is underway and will be completed in April. New testing of the moister in the slab came back as a positive so we do not need to seal the floor. Installation of the new gym floor will start the beginning of April.
Drywall work under the stairs was completed, the setting of the acoustical ceiling tiles has been finished. Installation of the interior doors was completed. Paint work is underway and will be completed in April. New testing of the moister in the slab came back as a positive so we do not need to seal the floor. Installation of the new gym floor will start the beginning of April.
UPCOMING ACTIVITIES:
The installation of the gym floor and the resurfacing of the old gym floor will take place. Paint work on the addition will be finished as the paint the drywall and the concrete in the lower stair tower continue as well as the handrails. The work on the addition will continue once we have the redesign of the kitchen from JRW.
The installation of the gym floor and the resurfacing of the old gym floor will take place. Paint work on the addition will be finished as the paint the drywall and the concrete in the lower stair tower continue as well as the handrails. The work on the addition will continue once we have the redesign of the kitchen from JRW.
PROJECT SCHEDULE:
82%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|