Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
May 2019
WORK ACTIVITIES:
The utilities have all been identified and relocated from under the new gym foundation. The footings have been excavated and placement of footing forms and rebar has begun.
The utilities have all been identified and relocated from under the new gym foundation. The footings have been excavated and placement of footing forms and rebar has begun.
UPCOMING ACTIVITIES:
Placement of rebar for footing and forming will continue, once the forms are ready the footings will be poured followed by the forming and pouring of the walls. Once the walls are poured dampproofing and below grade insulation will occur
Placement of rebar for footing and forming will continue, once the forms are ready the footings will be poured followed by the forming and pouring of the walls. Once the walls are poured dampproofing and below grade insulation will occur
PROJECT SCHEDULE:
5%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|