Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
May 2020
WORK ACTIVITIES:
The gym addition has been completed. The demo and framing of the new Kitchen addition are underway as the exterior walls have all been framed. The existing gym floor has been ground down and refinished like the new gym floor. Site work has been on hold as a new design is being put together by JRW.
The gym addition has been completed. The demo and framing of the new Kitchen addition are underway as the exterior walls have all been framed. The existing gym floor has been ground down and refinished like the new gym floor. Site work has been on hold as a new design is being put together by JRW.
UPCOMING ACTIVITIES:
Kitchen addition will continue into July when everything will be complete, and the building turned over to the district.
Kitchen addition will continue into July when everything will be complete, and the building turned over to the district.
PROJECT SCHEDULE:
86%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|