Lincoln Elementary School Addition

MONTHLY PROJECT UPDATES

May 2020


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:
The gym addition has been completed.  The demo and framing of the new Kitchen addition are underway as the exterior walls have all been framed.  The existing gym floor has been ground down and refinished like the new gym floor.  Site work has been on hold as a new design is being put together by JRW.
UPCOMING ACTIVITIES:
Kitchen addition will continue into July when everything will be complete, and the building turned over to the district.
Kitchen addition framing
Concrete wall painted
Gym floor finished
Kitchen addition framed
Storage room framed

PROJECT SCHEDULE:

86%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com