Lincoln Elementary School Addition
MONTHLY PROJECT UPDATES
September 2019
WORK ACTIVITIES:
Slabs have been poured in the gym and hallway. The masonry work is underway and progressing very well. Electrical work is being done in the masonry wall as it goes up.
Slabs have been poured in the gym and hallway. The masonry work is underway and progressing very well. Electrical work is being done in the masonry wall as it goes up.
UPCOMING ACTIVITIES:
Masonry work will continue until about the middle of October. Once the masonry work is complete the steel joist and deck will arrive for the roof structure. Once the steel is set the installation of the roof will begin. Some additional site work and concrete will occur while the steel is being done for the exterior stairways.
Masonry work will continue until about the middle of October. Once the masonry work is complete the steel joist and deck will arrive for the roof structure. Once the steel is set the installation of the roof will begin. Some additional site work and concrete will occur while the steel is being done for the exterior stairways.
PROJECT SCHEDULE:
38%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|