Your Project Updates
  • Madison SD 321 Bond Projects
  • Madison SD 321 Bond Projects
Search by typing & pressing enter

YOUR CART

Madison High School Additions

MONTHLY PROJECT UPDATES

April 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:

Classroom – MEP trim-out is complete. The final coat of paint has been applied. The Lab casework and epoxy countertops have been installed. The offices and electrical room grid ceilings have been finished. Final cleaning has begun on the second floor. Expansion joints have been caulked on the exterior of the classrooms. Frost walls have been poured for the entrances to the classrooms. Installation of the pre-cast concrete caps has been completed.

​Gym – Slab was poured early in the month. Once the slab cured the MEPF rough-in began. Block filling and paint has begun. The openings in the masonry have been closed-up. The drywall for the office in the wrestling room and storage have been hung, taped, and primed. MEPF work in wrestling room has been completed. Frost walls have been poured for the entrances to the gym. Installation of the pre-cast concrete caps has started and will be finished in May. The fire sprinkler tie-ins are complete, and the addition of the system is over half way complete.
​
UPCOMING ACTIVITIES:

Classroom – Exterior side walk and landscaping to happen in May, weather dependent. The parapet cap will be installed in May.

Gym – The parapet cap will be installed in May. Side walk on the gym will start in May and should be complete by months end. All mechanical units to set so all tie-ins can be completed. Paint work in the gym will continue in May and should be finished before the end of the month. The hardwood flooring is scheduled to be delivered the last week in May to start acclimating with installation starting in June.
​
Lab casework delivered-classroom
Lab casework installation-classroom
Handrails finished-classroom
Lab casework and tops installed-classroom
Finished classroom
Masonry work for the East wall-gym
Slab poured-gym
MEP work for wrestling room-gym
Storefront frames installed at the vestibule-gym
MEP work completed in corridor-gym

PROJECT SCHEDULE:

79%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.