Madison High School Additions
MONTHLY PROJECT UPDATES
April 2019
WORK ACTIVITIES:
Classroom – MEP trim-out is complete. The final coat of paint has been applied. The Lab casework and epoxy countertops have been installed. The offices and electrical room grid ceilings have been finished. Final cleaning has begun on the second floor. Expansion joints have been caulked on the exterior of the classrooms. Frost walls have been poured for the entrances to the classrooms. Installation of the pre-cast concrete caps has been completed.
Gym – Slab was poured early in the month. Once the slab cured the MEPF rough-in began. Block filling and paint has begun. The openings in the masonry have been closed-up. The drywall for the office in the wrestling room and storage have been hung, taped, and primed. MEPF work in wrestling room has been completed. Frost walls have been poured for the entrances to the gym. Installation of the pre-cast concrete caps has started and will be finished in May. The fire sprinkler tie-ins are complete, and the addition of the system is over half way complete.
Classroom – MEP trim-out is complete. The final coat of paint has been applied. The Lab casework and epoxy countertops have been installed. The offices and electrical room grid ceilings have been finished. Final cleaning has begun on the second floor. Expansion joints have been caulked on the exterior of the classrooms. Frost walls have been poured for the entrances to the classrooms. Installation of the pre-cast concrete caps has been completed.
Gym – Slab was poured early in the month. Once the slab cured the MEPF rough-in began. Block filling and paint has begun. The openings in the masonry have been closed-up. The drywall for the office in the wrestling room and storage have been hung, taped, and primed. MEPF work in wrestling room has been completed. Frost walls have been poured for the entrances to the gym. Installation of the pre-cast concrete caps has started and will be finished in May. The fire sprinkler tie-ins are complete, and the addition of the system is over half way complete.
UPCOMING ACTIVITIES:
Classroom – Exterior side walk and landscaping to happen in May, weather dependent. The parapet cap will be installed in May.
Gym – The parapet cap will be installed in May. Side walk on the gym will start in May and should be complete by months end. All mechanical units to set so all tie-ins can be completed. Paint work in the gym will continue in May and should be finished before the end of the month. The hardwood flooring is scheduled to be delivered the last week in May to start acclimating with installation starting in June.
Classroom – Exterior side walk and landscaping to happen in May, weather dependent. The parapet cap will be installed in May.
Gym – The parapet cap will be installed in May. Side walk on the gym will start in May and should be complete by months end. All mechanical units to set so all tie-ins can be completed. Paint work in the gym will continue in May and should be finished before the end of the month. The hardwood flooring is scheduled to be delivered the last week in May to start acclimating with installation starting in June.
PROJECT SCHEDULE:
79%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|