Madison High School Additions

MONTHLY PROJECT UPDATES

August 2018


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:
Classroom – The masonry contractor finished the bearing walls in the hallway and have moved to work on the stairs.  Steel was delivered and embeds and plates have been installed.  Steel erectors will start their work, once the masonry contractor has moved to the gym. 
 
Gymnasium – The scaffolding was delivered on the gym side and the masonry contractor started their first lift as they waited for material at the classroom.
UPCOMING ACTIVITIES: 
Classroom – The erection of the structural steel should begin the week of September 10th. Once the steel contractor has moved closer to the existing building, there will be more demo to be completed.
 
Gymnasium – The masonry contractor will being setting the CMU block at mid September and will work into November to complete their work.  The MEP rough-in will be placed in the block as the masons continue to go vertical with the block walls.
Masonry work.
Masonry work.
Masonry work.
Masonry work.
Bearing wall.
Bearing wall.

PROJECT SCHEDULE:

24%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.