WORK ACTIVITIES:
Gym – Installation of the Gym floor was completed along with most of the punch list items
Gym – Installation of the Gym floor was completed along with most of the punch list items
UPCOMING ACTIVITIES:
Gym – Installation of the Owner supplied bleachers.
Gym – Installation of the Owner supplied bleachers.
PROJECT SCHEDULE:
93%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|