Madison High School Additions
MONTHLY PROJECT UPDATES
February 2019
WORK ACTIVITIES:
Classroom – Taping of the drywall was completed on the 1st and 2nd floor. Installation of the cabinetry was completed on the 2nd floor. Installation of the grid for the acoustical ceiling was completed on the 1st and 2nd floor. The data was roughed in on both floors.
Gym – The joist and deck have been installed over the gym. The roofing began over the wrestling room and they are about halfway done with the roof over the gym. The area for the skylights has been cut out and framed. The window has been relocated from the existing building (the health room) to the wrestling room. The doorway has been cut for the wrestling room. In louvers in the main gym have been removed and the opening has been infilled with CMU block.
Classroom – Taping of the drywall was completed on the 1st and 2nd floor. Installation of the cabinetry was completed on the 2nd floor. Installation of the grid for the acoustical ceiling was completed on the 1st and 2nd floor. The data was roughed in on both floors.
Gym – The joist and deck have been installed over the gym. The roofing began over the wrestling room and they are about halfway done with the roof over the gym. The area for the skylights has been cut out and framed. The window has been relocated from the existing building (the health room) to the wrestling room. The doorway has been cut for the wrestling room. In louvers in the main gym have been removed and the opening has been infilled with CMU block.
UPCOMING ACTIVITIES:
Classroom – Flooring will begin about the middle of March with the grinding and staining of the concrete on the 2nd floor followed by the 1st floor. The installation of the carpet will follow just after the staining of the concrete. The lights will be installed in the grid ceiling along with all other MEP trim-out items.
Gym – The masons will work on the two east walls for the gym so the roofing can be completed. Ground thaw heaters will be placed in the gym so the earth worker can prep for the slab.
Classroom – Flooring will begin about the middle of March with the grinding and staining of the concrete on the 2nd floor followed by the 1st floor. The installation of the carpet will follow just after the staining of the concrete. The lights will be installed in the grid ceiling along with all other MEP trim-out items.
Gym – The masons will work on the two east walls for the gym so the roofing can be completed. Ground thaw heaters will be placed in the gym so the earth worker can prep for the slab.
PROJECT SCHEDULE:
62%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|