Madison High School Additions
MONTHLY PROJECT UPDATES
January 2019
WORK ACTIVITIES:
Classroom – Drywall has been completed on the 2nd floor. All MEP rough-in has been completed in the ceiling. Glazing was installed.
Gym – The decking was placed at the wrestling room and the floor was poured. The masons finished the south wall. The joist and deck was placed at the roof of the wrestling room.
Classroom – Drywall has been completed on the 2nd floor. All MEP rough-in has been completed in the ceiling. Glazing was installed.
Gym – The decking was placed at the wrestling room and the floor was poured. The masons finished the south wall. The joist and deck was placed at the roof of the wrestling room.
UPCOMING ACTIVITIES:
Classroom – The primer will be applied now that the drywall is complete on the 2nd floor, followed by the first coat of paint. The heat pumps on the 2nd floor will be turned on. Fiber will be pulled in the building on both floors. Installation of the grid ceiling will begin on the second floor about the middle of the month. The painting of 1st floor will begin about the middle of the month followed by the installation of the grid ceiling.
Gym – Installation of the joist and deck will occur on the main roof. The roofing over the wrestling room will begin about the middle of the month.
Classroom – The primer will be applied now that the drywall is complete on the 2nd floor, followed by the first coat of paint. The heat pumps on the 2nd floor will be turned on. Fiber will be pulled in the building on both floors. Installation of the grid ceiling will begin on the second floor about the middle of the month. The painting of 1st floor will begin about the middle of the month followed by the installation of the grid ceiling.
Gym – Installation of the joist and deck will occur on the main roof. The roofing over the wrestling room will begin about the middle of the month.
PROJECT SCHEDULE:
54%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|