Madison High School Additions

MONTHLY PROJECT UPDATES

January 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:

​Classroom – Drywall has been completed on the 2nd floor. All MEP rough-in has been completed in the ceiling.  Glazing was installed. 

​Gym – The decking was placed at the wrestling room and the floor was poured.  The masons finished the south wall.  The joist and deck was placed at the roof of the wrestling room.
 
UPCOMING ACTIVITIES: 

​Classroom – The primer will be applied now that the drywall is complete on the 2nd floor, followed by the first coat of paint.  The heat pumps on the 2nd floor will be turned on.  Fiber will be pulled in the building on both floors.  Installation of the grid ceiling will begin on the second floor about the middle of the month.  The painting of 1st floor will begin about the middle of the month followed by the installation of the grid ceiling.

Gym – Installation of the joist and deck will occur on the main roof.  The roofing over the wrestling room will begin about the middle of the month.
Hanging drywall-classromm
MEP rough in-classroom
Vestibule built
Drywall taped-classromm
Drywall primed-classroom
CMU work-gym
CMU work on South wall-gym
Preparing to set steel joists-gym
Steel joists-gym

PROJECT SCHEDULE:

54%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com