Madison High School Additions
MONTHLY PROJECT UPDATES
June 2018
WORK ACTIVITIES:
Classroom – The footing trenches were excavated, footing and foundation concrete poured, dampproofing applied, foundation backfilled, and the interior ridged insulation placed on the interior of the foundation wall. Underground plumbing started and will continue into mid-July. Demo for the classroom tie-in began around the end of the month and all mechanical, electrical, plumbing and fire sprinkler (MEPF) lines capped for future tie-in.
Gymnasium – The footing trenches were excavated, and footing and foundation concrete was poured.
Classroom – The footing trenches were excavated, footing and foundation concrete poured, dampproofing applied, foundation backfilled, and the interior ridged insulation placed on the interior of the foundation wall. Underground plumbing started and will continue into mid-July. Demo for the classroom tie-in began around the end of the month and all mechanical, electrical, plumbing and fire sprinkler (MEPF) lines capped for future tie-in.
Gymnasium – The footing trenches were excavated, and footing and foundation concrete was poured.
UPCOMING ACTIVITIES:
Classroom – Masonry work will begin about the middle of July once the slab is poured and had time to cure. Structural steel will begin by the end of July.
Gymnasium – The walls will be backfilled the second week of July, in preparation for underground MEP work to begin. Once the underground work is complete the slab will be poured.
Classroom – Masonry work will begin about the middle of July once the slab is poured and had time to cure. Structural steel will begin by the end of July.
Gymnasium – The walls will be backfilled the second week of July, in preparation for underground MEP work to begin. Once the underground work is complete the slab will be poured.
PROJECT SCHEDULE:
6%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|