Madison High School Additions

MONTHLY PROJECT UPDATES

June 2018


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:
Classroom – The footing trenches were excavated, footing and foundation concrete poured, dampproofing applied, foundation backfilled, and the interior ridged insulation placed on the interior of the foundation wall.  Underground plumbing started and will continue into mid-July.  Demo for the classroom tie-in began around the end of the month and all mechanical, electrical, plumbing and fire sprinkler (MEPF) lines capped for future tie-in.
 
Gymnasium – The footing trenches were excavated, and footing and foundation concrete was poured.
UPCOMING ACTIVITIES: 
Classroom – Masonry work will begin about the middle of July once the slab is poured and had time to cure.  Structural steel will begin by the end of July.
 
Gymnasium – The walls will be backfilled the second week of July, in preparation for underground MEP work to begin.  Once the underground work is complete the slab will be poured.
Classroom - Foundation wall concrete forms stripped.
Classroom - Underground plumbing work.
Classroom - Demo work for building tie-in.
Gym - Foundation walls formed.
Gym - Foundation walls formed.
Gym - Footings being formed.
Classroom - Footings.
Classroom - Footings.

PROJECT SCHEDULE:

6%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com