Madison High School Additions
MONTHLY PROJECT UPDATES
May 2018
WORK ACTIVITIES:
Classroom – The area has been cleared and grubbed and the utilities have been capped and relocated in preparation for the exaction of footings.
Gymnasium – The area has been cleared and grubbed and the utilities have been capped and relocated in preparation for the exaction of footings.
Classroom – The area has been cleared and grubbed and the utilities have been capped and relocated in preparation for the exaction of footings.
Gymnasium – The area has been cleared and grubbed and the utilities have been capped and relocated in preparation for the exaction of footings.
UPCOMING ACTIVITIES:
Classroom – Excavation for the footings will start the first week of June and forming of the footings will begin immediately following excavation. Once the footings have been formed, rebar will be set and concrete will be poured. Once the footings are poured the stem walls will be formed, rebar placed and poured. As soon as the foundation walls are complete, the underground work will commence in preparation for pouring the concrete slab. CMU (Concrete Masonry Units, aka, Concrete Block) work should start about the end of June.
Gymnasium – Excavation for the footings will start the second week of June and forming of the footings will begin immediately following excavation. Once the footings have been formed, rebar will be set and concrete will be poured. Once the footings are poured the stem walls will be formed, rebar placed and poured. As soon as the foundation walls are complete the underground work will happen in preparation for pouring the slab.
Classroom – Excavation for the footings will start the first week of June and forming of the footings will begin immediately following excavation. Once the footings have been formed, rebar will be set and concrete will be poured. Once the footings are poured the stem walls will be formed, rebar placed and poured. As soon as the foundation walls are complete, the underground work will commence in preparation for pouring the concrete slab. CMU (Concrete Masonry Units, aka, Concrete Block) work should start about the end of June.
Gymnasium – Excavation for the footings will start the second week of June and forming of the footings will begin immediately following excavation. Once the footings have been formed, rebar will be set and concrete will be poured. Once the footings are poured the stem walls will be formed, rebar placed and poured. As soon as the foundation walls are complete the underground work will happen in preparation for pouring the slab.
PROJECT SCHEDULE:
4%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|