Madison High School Additions

MONTHLY PROJECT UPDATES

May 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:

Classroom – Site Concrete has been completed.  Finishing touches in the Lab are underway and will be completed in June.
Gym – The parapet cap was installed in May. Sidewalk on the gym started in May and will continue into June.  All mechanical units to be set so all tie-ins can be completed.  Paint work in the gym will continue in May and wil finish before the end of the month.  The hardwood flooring was delivered the last week in May to start acclimating with installation starting in June.
UPCOMING ACTIVITIES:

Classroom –  Punchlist for the Labs will be completed.  Landscape to be completed.
Gym – The installation of the gym floor will begin.  Once the gym floor is completed the installation of the gym equipment will begin.  Overhead coiling doors have been scheduled and should be installed towards the end of the month.  Cabinetry in the concession area should begin about the middle of the month.

​
Finished classroom
Finished lab
Finished stairs
New sidewalk
Painting finished in gym
Side walk prep
Plumbing installation at restrooms
Glazing installed at gym vestibule
Wrestling room painted
Classrooms

PROJECT SCHEDULE:

82%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com