Madison High School Additions
MONTHLY PROJECT UPDATES
November 2018
WORK ACTIVITIES:
Classroom – Roofing finished early in November. The erection of the stairs began early in the month and was completed by mid-month. The framing of the first floor finished in the first week followed by the framing of the second floor. Both were completed by the end of the month. Once framing was far enough along, MEPF rough-in began. The first floor interior walls were completed by the end of the month. Masonry work is continuing throughout the interior.
Gymnasium – The exterior masonry work is continuing. The interior work began and will continue off and on through March. MEP rough-in has started on the interior walls.
Classroom – Roofing finished early in November. The erection of the stairs began early in the month and was completed by mid-month. The framing of the first floor finished in the first week followed by the framing of the second floor. Both were completed by the end of the month. Once framing was far enough along, MEPF rough-in began. The first floor interior walls were completed by the end of the month. Masonry work is continuing throughout the interior.
Gymnasium – The exterior masonry work is continuing. The interior work began and will continue off and on through March. MEP rough-in has started on the interior walls.
UPCOMING ACTIVITIES:
Classroom – Drywall will begin with insulation soon to follow. MEPF will continue in the ceiling and will be completed by the end of the month. Taping and texturing work will begin on the first floor and will carry into January. The masons will finish all interior walls by mid-month. The exterior veneer work will start the beginning of the month and will continue through January.
Gymnasium – Tenting has been relocated to finish the corridor and ticket area. Once this area is complete, they will move to the bearing wall. The installation of the steel and decking for the wrestling room will start in December and will finish early in January.
Classroom – Drywall will begin with insulation soon to follow. MEPF will continue in the ceiling and will be completed by the end of the month. Taping and texturing work will begin on the first floor and will carry into January. The masons will finish all interior walls by mid-month. The exterior veneer work will start the beginning of the month and will continue through January.
Gymnasium – Tenting has been relocated to finish the corridor and ticket area. Once this area is complete, they will move to the bearing wall. The installation of the steel and decking for the wrestling room will start in December and will finish early in January.
PROJECT SCHEDULE:
43%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|