Madison High School Additions
MONTHLY PROJECT UPDATES
September 2018
WORK ACTIVITIES:
Classroom – Structural steel is well underway with the erector setting steel columns and joist. Masonry work has been completed at the stair tower.
Gymnasium – Masonry work has begun. The electrical rough-in started with the masonry work so to keep the conduit in the block. Setting of the exterior doors frames has started as well.
Classroom – Structural steel is well underway with the erector setting steel columns and joist. Masonry work has been completed at the stair tower.
Gymnasium – Masonry work has begun. The electrical rough-in started with the masonry work so to keep the conduit in the block. Setting of the exterior doors frames has started as well.
UPCOMING ACTIVITIES:
Classroom – The erection of the structural steel should be complete the first week of October. Metal stud work will begin about the beginning of October and should be finished with the exterior framing by the middle of the month. They will then move to framing the interior walls. Mechanical/Plumbing/Electrical rough-in should start about the middle of the October.
Gymnasium – Masonry and electrical work will continue through October. Some plumbing underground will start towards the end of the month.
Classroom – The erection of the structural steel should be complete the first week of October. Metal stud work will begin about the beginning of October and should be finished with the exterior framing by the middle of the month. They will then move to framing the interior walls. Mechanical/Plumbing/Electrical rough-in should start about the middle of the October.
Gymnasium – Masonry and electrical work will continue through October. Some plumbing underground will start towards the end of the month.
PROJECT SCHEDULE:
36%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|