WORK ACTIVITIES:
Classroom – Structural steel is well underway with the erector setting steel columns and joist.  Masonry work has been completed at the stair tower.
 
Gymnasium – Masonry work has begun.  The electrical rough-in started with the masonry work so to keep the conduit in the block.  Setting of the exterior doors frames has started as well.
UPCOMING ACTIVITIES: 
Classroom – The erection of the structural steel should be complete the first week of October.  Metal stud work will begin about the beginning of October and should be finished with the exterior framing by the middle of the month.  They will then move to framing the interior walls.  Mechanical/Plumbing/Electrical rough-in should start about the middle of the October.
 
Gymnasium – Masonry and electrical work will continue through October.  Some plumbing underground will start towards the end of the month.
Classroom under construction.
Setting joists.
Setting joists.
Installing bracing.
Steel work.
Stairwell complete.
Joist and deck in hallway.

PROJECT SCHEDULE:

36%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.