Madison High School Fieldhouse
MONTHLY PROJECT UPDATES
July 2020
WORK ACTIVITIES:
CMU Structure completed, MEP work under the Southern floor slab was completed and building slab was poured for the Southern section of the building. Wood Framing commenced for the southern section of the building, and Main building steel structure erection was commenced. Site grading was recommenced, building was backfilled around the foundation walls, site grading was commenced
CMU Structure completed, MEP work under the Southern floor slab was completed and building slab was poured for the Southern section of the building. Wood Framing commenced for the southern section of the building, and Main building steel structure erection was commenced. Site grading was recommenced, building was backfilled around the foundation walls, site grading was commenced
UPCOMING ACTIVITIES:Steel Structure Erection is planned to be completed during the month of August, building enclosure finishes will be commenced, Building MEP rough-in will be commenced, site grading and utility systems will be in progress
PROJECT SCHEDULE:
35%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|