Madison High School Fieldhouse

MONTHLY PROJECT UPDATES

June 2020


previous month
ALL BOND PROJECTS
next month

WORK ACTIVITIES:

Earth workers was able to clear and grub the site.  Building footprint was excavated and structural fill placed. Footings have been over excavated and brought back up with structural fill per the Geotech.  Footings have been placed and forming of walls started.
UPCOMING ACTIVITIES:
Concrete work will continue with the forming and pouring of the concrete walls.  Once the walls are complete the masonry work will begin.  Footings for the front of the building will start as well as the concrete.
Over excavation for footings
Footings placed and stripped
Walls formed
Footings formed

PROJECT SCHEDULE:

26%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com