Madison High School Fieldhouse
MONTHLY PROJECT UPDATES
June 2020
WORK ACTIVITIES:
Earth workers was able to clear and grub the site. Building footprint was excavated and structural fill placed. Footings have been over excavated and brought back up with structural fill per the Geotech. Footings have been placed and forming of walls started.
Earth workers was able to clear and grub the site. Building footprint was excavated and structural fill placed. Footings have been over excavated and brought back up with structural fill per the Geotech. Footings have been placed and forming of walls started.
UPCOMING ACTIVITIES:
Concrete work will continue with the forming and pouring of the concrete walls. Once the walls are complete the masonry work will begin. Footings for the front of the building will start as well as the concrete.
Concrete work will continue with the forming and pouring of the concrete walls. Once the walls are complete the masonry work will begin. Footings for the front of the building will start as well as the concrete.
PROJECT SCHEDULE:
26%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|