Madison High School Sports Complex
MONTHLY PROJECT UPDATES
April 2019
WORK ACTIVITIES:
The drainage rock has been placed on the turf field. The prep work of the track for asphalt is nearly completed. Curb, gutter, and asphalt has been completed on 13th. Tie-ins between University and 13th have been completed. Sprinkler system is complete in the track along with the laying of the sod. The roofing of the Home Concessions and visitor ticket booth have been completed. Installation of the track bleachers has been completed. The track curbing and drain system have been completed and all concrete for track disciplines have been poured.
The drainage rock has been placed on the turf field. The prep work of the track for asphalt is nearly completed. Curb, gutter, and asphalt has been completed on 13th. Tie-ins between University and 13th have been completed. Sprinkler system is complete in the track along with the laying of the sod. The roofing of the Home Concessions and visitor ticket booth have been completed. Installation of the track bleachers has been completed. The track curbing and drain system have been completed and all concrete for track disciplines have been poured.
UPCOMING ACTIVITIES:
The masons will top out the west face of the grand stands early in May. Masonry work under the grand stands will continue through May. MEP rough-in and preparation for paint will occur in May. The e-layer for the turf field should start installation the end of May. Paving of the track will occur about the middle of May. Site flat work preparation will begin followed by the forming and placing of the concrete. Prep for mow strip and installation of site fencing to start around the end of the month.
The masons will top out the west face of the grand stands early in May. Masonry work under the grand stands will continue through May. MEP rough-in and preparation for paint will occur in May. The e-layer for the turf field should start installation the end of May. Paving of the track will occur about the middle of May. Site flat work preparation will begin followed by the forming and placing of the concrete. Prep for mow strip and installation of site fencing to start around the end of the month.
PROJECT SCHEDULE:
53%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|