Madison High School Sports Complex
MONTHLY PROJECT UPDATES
August 2018
WORK ACTIVITIES: The foundation has been completed for the home grandstands. Underground plumbing started and completed most of their work in preparation for the electrician. The curb and gutter was prepped and poured at the Southwest parking lot, the parking lot is almost to grade for asphalt. The track has been taken to grade and now pit run material is being placed in preparation for the track drain and curbing. The CPM piping for the storm water retention in the west stadium lot is being installed.
UPCOMING ACTIVITIES: Slabs will be poured at the grandstands starting the week of September 17th. Underground utilities will be stubbed into the grandstands about the middle of the month. Site utilities (water/sewer) to tie in at 12th west will be prepped and ready for tie in the week of spud harvest. Footing and foundation for the home side concessions will start the week of September 17th. Asphalt will be poured at the southwest parking lot about the middle of the month depending on an available crew. The CMP storm water piping will be installed and backfilled about the middle of the month so prep work for the curb and gutter and asphalt can be placed.
PROJECT SCHEDULE:
12%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|