Madison High School Sports Complex

MONTHLY PROJECT UPDATES

February 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:
​
​The masons finished the Home Concession Building, they have also progressed on the south section of the Grandstands. Installation of the steel joists on the stadium have been progressing from the North to South.  The grade beams for the visitor bleachers have been installed.  Work for the drain system of the turf field has continued. ​
UPCOMING ACTIVITIES:
​
​The masons will continue working on the south box of the Grandstands and will transition to the center box.  The joists and framing materials will arrive about mid-month for the Home Concessions stand so the framer can begin towards the end of the month.
Masonry work at the Grandstand
Grade beams for visitor bleachers
Masonry work at home concessions
Masonry work at Grandstand
Masonry work at home concessions

PROJECT SCHEDULE:

41%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com