Madison High School Sports Complex
MONTHLY PROJECT UPDATES
January 2019
WORK ACTIVITIES:
The installation of the 8” drain line was placed at the football field. The MEP under slab work was completed at the concession stand. The drain line for the stadium bleachers was installed. Masonry work began on the Grandstands with the East wall.
The installation of the 8” drain line was placed at the football field. The MEP under slab work was completed at the concession stand. The drain line for the stadium bleachers was installed. Masonry work began on the Grandstands with the East wall.
UPCOMING ACTIVITIES:
The masonry work will continue on the Grandstand as well as the Home Concession. The slab will be poured at the visitor ticket booth in preparation for CMU work. Steel work may begin about the end of the month.
The masonry work will continue on the Grandstand as well as the Home Concession. The slab will be poured at the visitor ticket booth in preparation for CMU work. Steel work may begin about the end of the month.
PROJECT SCHEDULE:
38%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|