Madison High School Sports Complex

MONTHLY PROJECT UPDATES

July 2019


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES:
​
Masonry Work has been completed.  MEP work has finished with final inspections completed.  The Football field turf has been completed.  Most of the site concrete has been completed with the exception of two mow strips.  Landscape is progressing.  Bleachers have been completed with the exception of a couple punch list items. Cleaning of the roads and parking lots have started.
UPCOMING ACTIVITIES:
​
Final punch list items for the bleachers.  Installation of the footings for the track scoreboard.  Pouring of the last two mow strips.  Landscaping of the North and South sides of the track and stadium.  Final cleaning of the roads and parking lots.​ 
​​
Stadium
Finished team room
Home concessions
Home concessions

PROJECT SCHEDULE:

88%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com