WORK ACTIVITIES: The site has been cleared and grubbed. The footings have been dug in preparation for the footings to be formed and poured at the beginning of July.
UPCOMING ACTIVITIES: Concrete work will begin for the grandstand slab the second week of July and will run through the end of the month. Earthwork will continue as the scrapers start to form the different areas of the project.
PROJECT SCHEDULE:
2%
Percent Complete
This project is being built for Madison School District #321
|