Madison High School Sports Complex
MONTHLY PROJECT UPDATES
March 2019
WORK ACTIVITIES:
The framing was started and completed at the Home Concessions Building. The installation of the joist is nearly complete and the decking is being installed. All underground work at the turf field has been completed and work for the drainage course of rock is underway. Masonry work will continue with the completion of the visitor ticket. Work at the grandstands continues.
The framing was started and completed at the Home Concessions Building. The installation of the joist is nearly complete and the decking is being installed. All underground work at the turf field has been completed and work for the drainage course of rock is underway. Masonry work will continue with the completion of the visitor ticket. Work at the grandstands continues.
UPCOMING ACTIVITIES:
The drainage rock will be placed on the turf field. The prepping of the track for asphalt will begin. Curb and gutter will be going in on 13th St. in preparation for asphalt. Tie between University and 13th St. will be underway. Sprinkler system in the track will begin. The roofing of the Home Concessions and grandstands will begin.
The drainage rock will be placed on the turf field. The prepping of the track for asphalt will begin. Curb and gutter will be going in on 13th St. in preparation for asphalt. Tie between University and 13th St. will be underway. Sprinkler system in the track will begin. The roofing of the Home Concessions and grandstands will begin.
PROJECT SCHEDULE:
44%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|
This project was designed by
JRW & Associates |
|
This website has been created to provide project updates only and is not a part of the District's website or managed by the District. Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.
|