Madison High School Sports Complex
MONTHLY PROJECT UPDATES
May 2019
WORK ACTIVITIES:
The masons topped out the west face of the grandstands early in May. Masonry work under the grandstands will continue through June. MEP rough-in work began and will continue through June. The e-layer for the turf field started being installed the end of May and will continue into June because of weather. Paving of the track occurred the middle of May. Site flat work preparation began followed by the forming and placing of the concrete and will continue into June. Installation of the visitor bleachers began and will continue into June.
The masons topped out the west face of the grandstands early in May. Masonry work under the grandstands will continue through June. MEP rough-in work began and will continue through June. The e-layer for the turf field started being installed the end of May and will continue into June because of weather. Paving of the track occurred the middle of May. Site flat work preparation began followed by the forming and placing of the concrete and will continue into June. Installation of the visitor bleachers began and will continue into June.
UPCOMING ACTIVITIES:
Masonry work will continue in the north and south box and should be completed by July. MEP rough-in will continue through June. The e-layer for the turf field will be completed by the middle of June, followed by the installation of the turf field. Track surfacing will begin about the 20th of June and will continue into July. Site flat work preparation will begin followed by the forming and placing of the concrete. Prep for mow strip and install of site fencing to start around the middle of the month. The installation of the visitor bleachers will finish about the middle of June. The installation of the grandstand bleachers will start about the middle of June and will continue into July.
Masonry work will continue in the north and south box and should be completed by July. MEP rough-in will continue through June. The e-layer for the turf field will be completed by the middle of June, followed by the installation of the turf field. Track surfacing will begin about the 20th of June and will continue into July. Site flat work preparation will begin followed by the forming and placing of the concrete. Prep for mow strip and install of site fencing to start around the middle of the month. The installation of the visitor bleachers will finish about the middle of June. The installation of the grandstand bleachers will start about the middle of June and will continue into July.
PROJECT SCHEDULE:
66%
Percent Complete
This project is being built for Madison School District #321
|
This project is being built by Headwaters Construction Company
|