Madison High School Sports Complex

MONTHLY PROJECT UPDATES

October 2018


PREVIOUS MONTH
ALL BOND PROJECTS
NEXT MONTH

WORK ACTIVITIES: Water and sewer tie-in occurred the first week of October during Spud Harvest break. Curb and drain were installed at the track. Irrigation was run for the in-field of the track and the main line was completed around the job site. Curb and gutter were prepped and installed at the west stadium parking lot. Asphalt was laid at the west stadium parking lot. Underground electrical was run through the football field. Posts for the 4’ chain link fence around the football field were set in preparation for the ribbon curb. Walls for the home ticket, concessions, and visitor ticket offices were prepped and poured.
UPCOMING ACTIVITIES: Steel uprights for the home side grandstand will be installed early in the month in preparation for the CMU. Curbing for the north stadium parking lot will be set now that all storm drains in the parking lots have been set and completed. Asphalt for the north stadium parking lot is to be poured the second week of November. Prep and installation of curbing will take place around the middle of the month at 13th West. The subcontractor is set to arrive during the middle of the month and start installation of the track and stadium lights. The installation of the added field drain, at the bleachers, will begin at the end of the month. Curbing for the football field will begin at the North side of the field.
Site concrete at west stadium parking lot.
Placing fabric for CMP tank.
Pouring walls for home concessions.
Grandstand slabs poured.
West stadium parking lot poured.
Stadium site.
Stadium site.

PROJECT SCHEDULE:

25%
Percent Complete

This project is being built for Madison School District #321
msd321.com
This project is being built by Headwaters Construction Company
HeadwatersCC.com
This project was designed by
JRW & Associates
JRWA.com
Contact
This website has been created to provide project updates only and is not a part of the District's website or managed by the District.  Please submit any questions or comments to YourProjectUpdates.com through the Contact portal.